Next case study
Cumbernauld Academy & Theatre
View case study
You are using an outdated browser. Please upgrade your browser to improve your experience.
We provided Connection Design, 3D Model, Supply, Fabricate, Galvanise, Deliver and Install of Ethane Storage Tank in Grangemouth.
To enable the site to import and make use of feedstock (ethane) from the North American shale gas fields, a 60 000 cubic metre ethane storage tank is at the Grangemouth site. Together with associated import infrastructure including pipework (~4km) and modifications to the existing jetty this significant project is due to complete in August 2017 and has received support from the Governments in Holyrood and Westminster. Pipework on new high-level steel pipe bridges (~400 Tonnes) by Cairnhill c/w Galvanised finish (Supply & Install).
Total labour on site, incl. all scopes of work = 26 supported by a Project Management and a Fabrication Team
Scope of work includes Connection Design, 3D Model, Supply, Fabricate, Galvanise, Deliver and Install
Doosan Babcok for INEOS
Grangemouth
2017 to current
Approximately £1.5m of a £500m Project
Area 11 (30m bridge over Bo’ness Road x 10.5m overall height), we are currently planning to pre-assemble and fit-out with Pipework, full 30m section (3.3m wide x 3.8m high x 35 Tonnes) and transport as a unit to site for installation with a 500 Tonne Crane before reopening of Bo’ness Road.
Area 9 (3D Image) – 150m of Pipebridges (190t); Typical 12m spans
Final 18m section (4.5m wide) of Area 9A being loaded onto Low loader for escorted night movement
Cumbernauld Academy & Theatre
View case study